No.
An RFI means the BSR requires further information or clarification to complete its assessment. It does not necessarily mean that the building is unsafe or that the safety case will be refused.
The relatively short response period commonly provided for RFIs – often around seven days – is also an indication that the response does not necessarily require every underlying information gap to be physically resolved before you reply.
For example, if the RFI highlights that there is insufficient information about a particular part of the structure, it may not be realistic to specify, procure and complete an intrusive structural investigation within the response period.
Instead, the response may need to demonstrate that:
- the gap has been recognised
- its potential risk has been considered
- appropriate interim arrangements are in place
- further work has been defined and programmed.
The important question is therefore not simply:
"Can we close this gap in seven days?"
but:
"Can we demonstrate that we understand the gap and have a reasonable, risk-based plan for managing it?"
Next step
Talk to us about reviewing your building safety case
Already have a report? We can look at the risk argument and the evidence behind it.
Find out moreRelated questions
- I've received an RFI from the BSR about my safety case. What should I do?
Start by identifying what the BSR is asking you to demonstrate. An RFI is not a request for more documents — it is a regulatory question that needs a clear, risk-based answer.
- What if I cannot close an information gap before the BSR response deadline?
Be transparent. A safety case does not become stronger by disguising uncertainty. Explain what is unknown, why it matters, what is known, current controls and the planned programme.
- Can you resubmit a safety case report after a BSR refusal?
Yes — but the response should address the underlying risk and evidence issues, not just reword the report.
Building safety legislation, regulation and Building Safety Regulator guidance can change. This page is general information, not legal advice — always refer to current legislation and official guidance for your building.